The project consists of the demolition of existing sports hall and associated changing rooms and the construction of a new sports hall with attached two-storey changing facilities, gym and dance studio.
The project value is circa £2,011,000 and will be on site for 34 weeks in total, beginning in February 2014 starting with the site set up, isolation of services and demolition works.
The project value is circa £2,011,000 and will be on site for 34 weeks in total, beginning in February 2014 starting with the site set up, isolation of services and demolition works.